OC Transpo’s general manager says upgrades to the O-Train Line 1 East Extension’s track infrastructure are needed before pre-trial running of the system can commence. In a memo to council, Rick Leary, general manager of transit services, said OC Transpo will begin testing the full line between Tunney’s Pasture and Trim stations this weekend. Leary says testing on the east extension will then be put on pause for the week of Nov. 29 to allow for upgrades to track infrastructure. According to Leary, the upgrades are being done at the request of East-West Connectors, the subcontractor in charge of the Stage 2 extension, and will help to “increase system reliability.” The transit service will resume testing the full-length of the line once the upgrades have been completed, Leary says. “Full-line testing is expected to continue for a few weeks, while all system elements are exercised,” Leary said. While trains will run between Tunney’s Pasture and Trim stations during this exercise, customer will be required to disembark at Blair Station. The transit service delayed pre-trial running this fall after issues were detected with safety-critical software. On Sunday, OC Transpo successfully installed a software update. “We will continue to follow a staged approach to fully exercising all system elements, with the focus of increasing system reliability ahead of opening to the public,” Leary said. “This approach is helping to identify any necessary improvements before advancing to the next phase.” The memo did not provide a firm date for pre-trial running, but Leary says he will provide a timeline for testing activities to Council in December, “including when we are ready to begin trial running.” Pre-trial running that is expected to take at least a week and will be followed by a 21-day trial running period.