The head of OC Transpo has identified a checklist of items that he says need to be completed before the next phase of testing on the O-Train Line 1 East Extension can begin. A full complement of 23 trains has been running from Tunney’s Pasture Station to Trim Station this week to “exercise the system” as part of a staged approach toward opening the extension beyond Blair Station to passengers. In a memo to city councillors and the mayor on Thursday, Transit Services general manager Rick Leary said the exercise has demonstrated six items he says need to be addressed by the contractors Rideau Transit Maintenance (RTM), East-West Connectors (EWC) and Hitachi before the pre-trial running step can start. The items are: “Identifying these issues is a normal part of the testing process and a fundamental objective of the current phase of testing. It is important that we identify issues at this stage to provide sufficient opportunity to make necessary corrections and improvements well in advance of proceeding to Pre-Trial Running and Trial Running,” Leary wrote. “RTM, EWC and their subcontractors have technical experts engaged on action plans to address these items.” The opening of the long-awaited eastern extension of O-Train Line 1 requires several key steps. The pre-trial running phase will last at least one week. That will be followed by the trial running phase, which requires the system demonstrate operability with no significant errors for a minimum of 21 days. Final checks and preparations will take place once trial running is complete and only then can the extension accept passengers. Testing dates pushed back Pre-trial running was initially expected to begin in October, but it was delayed to November after an issue was detected with the train’s safety-critical software. After that, OC Transpo said it would “exercise” the line during the week of Nov. 22, which would be a separate activity from pre-trial running. Leary said full line testing will continue until the end of the service day on Friday. Train operation between Blair and Trim stations will be suspended from Nov. 28 to Dec. 5, at EWC’s request. “EWC will complete preparatory work for upgrades to an element of the traction power system along the tracks. The upgrades increase operational flexibility when managing service disruptions and shorten the time required to return to normal operations. This work has been prioritized to reduce impacts once the East Extension is in operation,” he said. Full line testing is expected to resume on Dec. 6. “We are assessing operations and need to see progress on the items above to determine readiness to advance to the next phase of testing. In early December, I will provide an update on the work performed over the course of next week and the next steps in the process of testing, including pre-trial running,” said Leary. Earlier this month, Mayor Mark Sutcliffe defended the pace of progress on the extension, saying the city does not want to repeat the mistakes that were made during the launch of Stage 1 of LRT in 2019.