18 residents opposed to a 29-acre battery energy storage project near Port Elgin, Ont. got to share their concerns with the company and Saugeen Shores council this week. Opponents had concerns about safety of the proposed facility, the loss of farmland, and what would happen in case of a fire at the industrial complex. The proposed project would entail 344 lithium iron phosphate battery containers pulling electricity from the grid during times of overproduction and low demand, storing that energy, and then putting it back on the grid when demand is high. It’s one of 29 such projects either in operation, or in development in Ontario. Opponents, including the National Farmer’s Union, suggested 320 acres of farmland is lost to development in Ontario each day. Projects like this make that situation worse for incremental energy gains, opponents say. The project proponent, Neoen Canada, says the project is important to balance out Ontario’s energy system, specifically using power from wind turbines, that typically churn at night when demand is low. They believe the site, located two concessions south of Port Elgin, is suitable and took years to finalize. “It’s a comprehensive process. We consider a lot of constraints, and we are really convinced that the site that we have selected with the Saugeen Ojibway Nation and is a good site for that project,” said Neoen Provincial Director, Benoit Pinot de Villechenon. The project is endorsed by the Saugeen Ojibway Nation but is awaiting zoning amendment approvals from Saugeen Shores council and Bruce County council. The decisions won’t come until early next year. If those approvals are ultimately granted, Neoen says construction could begin late next year, and the 20-year project would be operational by the end of 2028.