The city marked what it calls a “major achievement” in the first phase of the Capital Line South LRT Extension on Wednesday afternoon with the reopening of the intersection at 9 Avenue west of 111 Street. Drivers will now have access to restored lanes in each direction on 111 Street from south of Blackmud Creek Bridge to Anthony Henday Drive. The city and Ledcor, the contractor for the project, hope the changes reduce traffic congestion for 111 Street commuters. The area was closed in August, with residents in the Twin Brooks neighbourhood losing full access twice during the construction season. “The full closure at 9 Avenue allowed Ledcor to complete critical underground, road and utility work for the future alignment, and Edmontonians can now see track crossing the intersection,” Eva Cheung, LRT expansion supervisor, said in a media release. “Undergoing two full intersection closures within a community that already has limited access has been challenging. We are grateful for the patience of residents, businesses and commuters as crews worked long hours to achieve this major milestone.” Construction on the Capital Line South LRT Extension began in May 2025. Phase 1 is expected to be done in 2029. It will ultimately extend the line 4.5 kilometres south and southwest from Century Park to the Heritage Valley Transit Centre and Park & Ride at Heritage Valley Trail and Ellerslie Road SW. With files from CTV News Edmonton’s Craig Ellingson